A new comprehensive project scheduling, monitoring, and management framework based on the critical chain under interval type 2 fuzzy uncertainty

S. Aramesh | V. Mohagheghi | Seyed Meysam Mousavi

URL :   http://research.shahed.ac.ir/WSR/WebPages/Report/PaperView.aspx?PaperID=137827
Date :  2020/08/31
Publish in :    Iranian Journal of Fuzzy Systems

Link :  https://ijfs.usb.ac.ir/article_5659.html
Keywords :Project scheduling, critical chain method, mathematical programming, project monitoring, resource-constrained project scheduling, interval type-2 fuzzy sets.

Abstract :
Projects require proper control and management techniques to achieve their de ned success criteria. Often projects end in longer periods and higher costs than planned. It is necessary to apply approaches that can keep the project close to its precedence goals and purposes. In this paper, a new framework is presented that is mainly concerned with properly managing project implementation and evaluation. In detail, the method has four main parts. First, a new mathematical programming is o ered to address project scheduling. The results of project scheduling are then applied in a critical chain method based approach under interval type-2 fuzzy uncertainty in the second part to both enhance project scheduling and address uncertainty. The third part of the approach is developed to monitor the project implementation process, and new thresholds are de ned to discuss corrective measures when necessary. Finally, the fourth part of the approach is designed to evaluate project implementation and reach an understanding of how the project is implemented. To display the applicability of the approach, a practical example is solved, and the process is step by step presented along with the comparative analysis.